Update on new timetable after December 12th

It has been a while since I have posted an update, but now there are a number of issues that are on the immediate agenda and are still likely to be at the time of the OBRAG AGM which will be held in late January (details of time, date and structure of meeting to follow by mid-December):

A – Problems with New Timetable

  • Chiltern Railways’ planned new timetable will involve a major change in the evening peak time services since the departures from London Marylebone for trains that stop at Islip that currently exist at 1535/1750/1921/2135 will change to 1535/1650/2007/2132 (with an additional but not ideal option of catching the 1850 from London and changing trains at Oxford Parkway).  This is a further blow to Islip-London commuters on top of the already less than ideal commuter service in the mornings.
  • Thank you to those who have already contacted Chiltern in a personal capacity to complain about this significant further degradation of the commuter service from Islip to London. OBRAG is looking into coordinating with interest groups within Islip to issue a joint letter of complaint to Chiltern Railways and to our MP to raise awareness, as well as contacting the press to express our concern and disappointment. I feel that rather than angry protest we need to try to put the most rational argument we can to Chiltern as to why they should maintain a decent commuter service from Islip to London and from Islip to Oxford. I have spoken to individuals about this but I would welcome people’s thoughts on how to make the most persuasive case.
  • I am still waiting to receive a full copy of the timetable from Chiltern (not very pleasing) though I believe there are some floating around so if anyone could please email me a copy that would be great. Also, any other concerns/comments about the changes that will be made would be much appreciated.

B – Positives

  • As a regular Islip-Oxford commuter, my experiences have been pretty good lately. It has been quite a while since I missed a bus or train due to delays, although I do still have to run occasionally.
  • The broken ticket machine in Islip was an annoyance for several weeks, but this has now been repaired.

C – Longer Term Objectives

  • OBRAG has been involved in liasing with other rail user groups on the Oxford-Bicester-Bletchley-Milton Keynes-Bedford line. As well as attempting to influence the Islip and Bicester rail services in a desirable direction now that we have a very good piece of infrastructure in place locally, I think we should not lose sight of the bigger picture of the need to support and encourage where we can the completion of the East-West rail project, which will also benefit us in increasing rail connectivity from Islip and Bicester in the longer term.
  • Eventually it might be desirable to move towards some kind of federal structure of user groups along the line in order to better co-ordinate activities and avoid unnecessary duplication. I suggest this as another topic for discussion at the AGM.

Update on impact of summer blockade on services

Please find below some further information about the impact of the rail works over the next few weeks on services through Bicester and Oxford Parkway.

The document below details a few minor changes to times of services from Oxford Parkway. The only major change is that the 7:14 from Oxford Parkway will not be running from 1st-5th August 2016.

Islip SX Blackade week 1 August 2016

There is also a 9 day closure on the line between Leamington Spa and Bicester North from 30 July until 7 August 2016.   For more information, please visit www.chilternrailways.co.uk/banbury-upgrade

FWD: Network Rail works summer blockade – 30 July to 14 August 2016

Forwarded message:

Network Rail works summer blockade – 30 July to 14 August 2016

This notification is for information only. These works are unconnected with East West Rail phase 1 works.

As part of Network Rail’s Railway Upgrade Plan, they will be carrying out major rail improvement work between Leamington Spa, Banbury, Bicester North, Oxford and Didcot Parkway this summer and lines will be closed for up to 16 days (30 July – 14 August 2016).

During this time Network Rail will be working throughout the Oxford Corridor on a number of projects which may be disruptive to lineside neighbours. However, please be assured, that Network Rail are working hard to minimise noise as much as possible, including limiting the working shift hours, and using techniques and equipment that are quieter than the standard methods we use across the country.

Download this information as a leaflet here.

WHAT WORK IS HAPPENING?

Aristotle Lane

Auger Piling may continue and minor associated works in preparation for the footbridge to demolished, and the new bridge to be lifted in.

  • 3–5 August: Auger Piling and minor associated works (7am-7pm)
  • 3–5 August: Ditch clearance (7am-7pm)

Castle Mill Stream

We continue our piling in preparation for the bridge deck reconstruction as per previous piling works. Please note Network Rail will be using a large crane to lift and install the bridge.

  • 30 July – 3 August: Auger piling (24hr working)
  • 3 – 8 August: Bridge reconstruction throughout (24hr working including track works).

Sheepwash Bridge

During the blockade we will be working on Sheepwash Bridge to upgrade the current track and install a cantilever walkway.

  • 30 July (12.01am) – 1 August (8am): Remove existing track and reinstate (24hr working)
  • 1 – 4 August: Install cantilever walkway – planned day shifts only but may require some 24hr working

Oxford Station

We will be delivering a package of works in preparation for the new Chiltern Railways Oxford to Marylebone service starting on the 12 December 2016.

  • 30 July (11pm) – 1 August (8am): Relay and tamping of the new Platform 1 & 2 track (24hr working)
  • 30 July – 7 August: Auger piling (24hr working)
  • 2 – 7 August: Installation of new platform inc brick laying (24hr working)

Botley Road Bridge

  • 1 – 5 August: Track repairs – maintenance of track fixing will involve drilling the concrete (7am-7pm)

Stone Meadow to Walton Well Bridge

  • 1 – 6 August: Track works inc welding and stressing (7am-7pm)

Sheepwash Bridge and Rewley Road area

  • 1 – 6 August: Track works inc points enhancements (7am-7pm)

Deliveries will be throughout, generally during day times with crane delivery in the early hours on the 2 August, and then being removed from site on the 8 August.

Contact Network Rail

I hope this information is helpful and we apologise for any inconvenience these essential works may cause.

However, if you have any additional questions or concerns about the work taking place in your area please call our dedicated 24-hour National Helpline on: 03457 11 41 41 or visit www.networkrail.co.uk/contactus

If you’d like regular updates during the blockade, please sign up to our newsletter by emailing Amy Harland at amy.harland@networkrail.co.uk.

FWD: NOTIFICATION OF WORKS ACTIVITY IN ISLIP – 12 July to 12 August 2016

Forwarded message:

Dear Resident and/or Parish Council member

NOTIFICATION OF WORKS ACTIVITY IN ISLIP – 12 July to 12 August 2016

The following is a summary of the proposed activity to the rail corridor in the Islip area.

This information is correct at time of writing. Please feel free to circulate it and encourage others to sign up for email updates (see details at end of email).

Station Approach will be closed at Islip station for a further period of 4 weeks from 12 July to 12 August 2016. The station car park will be closed, and pedestrian access to both platforms will be via the ramp on the other side of the rail corridor.

Works have continued beyond our anticipated finish date as the existing station car park was shown to lack adequate foundations. We have been instructed to undertake this remedial work whilst we are in the area to avoid future disruption to users and the village.

Finalisation of our works has been further delayed by local authority road works being conducted on Bletchingdon Road, and we have been asked to delay our works to complete resurfacing of the Station Approach junction until these are complete.

You have been sent this information as a previous correspondent/subscriber to our email notification service. If you wish to opt out of such notifications, please reply to this email with UNSUBSCRIBE as the subject. New subscribers can add their name to the mailing list by emailing us with SUBSCRIBE ISLIP as the subject.

Best wishes

Stella

Stella Whyte
Project Community Liaison – East West Rail Phase 1

3 Bessemer Close, Bicester OX26 6QE
email: swhyte@rsk.co.uk

24hr helpline: 0800 9788 233 or

helpdesk@bicestertooxfordcollaboration.com

http://bicestertooxfordcollaboration.com